The strip out of the old courthouse included removal of all non-structural and cosmetic elements, and required excavators and skid steer’s to be used on suspended slabs. Engineers were engaged to design a backpropping plan for the suspended slabs, and small crane winches were used to transport the machinery across the levels, through a staircase shaft that was removed.
The project included removal of old plant from the rooftop plant deck, and a final clean, handing the building back to the developers, to give it a new life.