In 2018, Abyss Demolition performed the demolition of the Acetylene Dock, Compressor Room, Test Shop and Shed Building at the BOC Rocklea site. Our A Class licenced and experienced asbestos crew removed asbestos prior to demolition. With the aid of a crane and boom lift, Abyss staff cut and lifted pieces of the concrete structure to ensure safe demolition of the dustbin. To ensure safe completion of this job at a live explosive infrastructure site, we used plasma cutting to dismantle the large structure.
Checkout our timelapse video of the BOC Rocklea Dustbin Demolition below.
Site Preparation
Engage engineers to collaborate on methodology
Applied for and secured local council permits for works
Establish exclusion zone within the premises
Safety
Safely removed asbestos, verified by air monitoring conducted by an independent licenced hygienist and clearance certificates